how did we optimise, earlier?

We efficiently resolved challenges being faced on site with major cut slopes. We enabled construction works to continue during the critical summer earthworks season.

Our services included detailed geological mapping, and interpretation, co-ordination of additional site investigations as well as undertaken significant slope stability analyses to ensure that every stage of the works met with the stringent requirements.

While we were at it, we were asked to optimise ground improvements at the Northern Tie-in – a tricky piece of work and designed a three-metre diameter pipe jack under the existing live State Highway embankment – contending with very low headroom of less than four metres. We didn’t move mountains, and we weren’t the main consultant – but we certainly optimised the Geotech.

expertise

location

Auckland

project team

We worked with Andy and his team through the past two earthwork seasons on a number of challenges -from stabilisation of large cut slopes in challenging ground. The solutions have been realistic, reasonable and constructable and a real ‘value add’ has been having some of our team regularly working out of Andy’s offices in true collaboration.

Phil Millership – Engineering Manager, Fletcher Acciona Joint Venture